On August 8, 2024, an extraordinary storm swept through Hudson, Ohio. A rain gauge just west of Hudson High School recorded nearly 7 inches that day, including more than 5 inches in just two hours.

 

Roads and neighborhoods flooded, even in places that had rarely reported flooding before.

 

Residents and City leaders faced difficult questions:

 

  • Why were some areas hit harder than others?
  • Was the problem an undersized pipe, a blocked culvert, an overflowing stream, or something more complicated?
  • Where should Hudson invest first to limit the impact of future storms?

 

The answers could not be found by looking at one flooded street at a time.

Resident Reports Revealed a Larger Pattern

 

After the storm, Hudson collected resident reports about flooding and property damage. The City then analyzed the information to find the hardest-hit locations. The largest concentration was in an area draining to an unnamed stream that flows into Tinkers Creek. A preliminary review documented 155 damage reports there, making it the highest priority for a more detailed study.

 

These individual accounts began to tell a larger story. Flooding was not confined to one subdivision or piece of infrastructure. Water was moving through a connected system of yards, streets, storm sewers, culverts, streams, and natural drainage paths.

 

Understanding What the Storm Exposed

 

Working with Hudson, ms consultants developed a model of the area’s drainage system. This model showed how rainfall and runoff moved across the land, through stream channels, and into and beyond the storm sewers.

 

The results were compared with resident reports, City input, and field information from the August 2024 storm.

 

Those results closely matched observed flooding patterns, providing a sound basis for evaluating the watershed—the area of land that drains to a common stream or outlet.

 

The analysis showed that Hudson was not facing one infrastructure failure, but multiple conditions contributing to flooding:

 

  • Less room for floodwater: Development had constrained natural drainage paths and reduced space where floodwater could spread and collect.
  • Older drainage system: Many older neighborhoods lacked basins to temporarily hold stormwater, and homes had been built right up against major drainage paths.
  • Restricted flows: Some roadway crossings and culverts restricted larger flows, causing backups.
  • No outlet: In other low-lying areas, there was no way for ponded water to leave, creating standing pools.

 

These conditions converged on flat, developed land along a drainage path. Fixing one location without knowing its impact elsewhere might not reduce flooding across the watershed. Worse, it could increase flooding for downstream communities and residents.

 

Testing Improvements Before Committing Funds

 

Potential improvements were tested in the model to see how each would affect flooding.

 

Some concepts offered local flood relief but little benefit across the watershed. One concept lowered water levels in one location but moved water downstream faster, raising water levels there.

 

The analysis helped Hudson avoid funding projects that might not do much to reduce flooding or might increase flooding elsewhere. This gave the City a stronger basis for future stormwater investments.

 

Just as important, the analysis established how those actions should work together. The recommendation was to first create upstream storage, then upgrade drainage routes and structures to redirect the flow and carry it through the area.

 

Hudson now has more than a list of possible projects. It has a roadmap for deciding which improvements to fund, in what order, and how each would help lessen flooding across the watershed.

A Significant Reduction in Flooding and a Clear Path Forward

 

For the modeled 100-year storm, the recommended strategy would:

 

  • Reduce the number of structures experiencing more than 0.5 feet of flooding by 28%.
  • Lower flood depths for 68% of the remaining affected structures by an average of 0.47 foot—just under six inches.

 

That reduction is significant.

 

Engineers note that as little as two feet of moving water against a typical home’s foundation can cause it to shift or collapse, resulting in substantial damage.

 

The August 2024 storm was well beyond what typical stormwater infrastructure can reasonably accommodate. The modeling helped Hudson understand how much relief the recommended improvements could provide.

 

The storm created urgency. Hudson’s leadership, residents’ local knowledge, and ms consultants’ analysis turned that urgency into a practical roadmap for the City.

 

Where Could Your Community Start?

 

With recurring flooding, aging infrastructure, and limited resources, knowing where to start can be difficult.

 

 Talk with our team to learn where to focus your community’s stormwater investments.

Get in touch

Love our projects? Interested in starting something exceptional?

Contact us and we would be happy to help.